Katie posh runs an upscale nail salon. the service process includes

Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses):

Activity 1: Welcome a guest. (1 minute)

Activity 2: Clip and file nails. (3 minutes)

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

Activity 3: Paint. (5 minutes)

Activity 4: Dry. (10 minutes)

Activity 5: Check out the customer. (4 minutes)

Three servers (S1, S2, and S3) offer the services in a workerLpaced line. The assignment of tasks to servers is the following:

S1 does Activity 1.

S2 does Activities 2 and 3.

S3 does Activities 4 and 5.

The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon.

PN1. Which resource is the bottleneck of the process?

PN2. What is the utilization of server 2? Assume that there is unlimited demand and that the process only admits customers at the rate of the bottleneck.

PN3. What is the average labor utilization of the servers? Assume that there is unlimited demand and that the process only admits customers at the rate of the bottleneck.

PN4. Assume a wage rate of $12 per hour. What are the direct labor costs for one customer?